Savoy Hotel – London

Originally opened in 1889 – This hotel was reinvented for the 21st century but retains its old fashioned glamour , blending two  aesthetics of English Edwardian & art deco seamlessly. With no two of the 268 rooms the same & many rooms retaining original features.

Astins were called in to take over this job from another contractor who failed to deliver, this made our start on site a rapid one having 64 site operatives & 5 working managers on site within 4 days. Taking over from others proved a labour intensive task Astins had to quality check every wall that had been built to ensure it met with Chorus Groups high standards.

Astins Performance on delivery & team commitment were highly praised by Chorus.

“Excellent attitude on site overall. All operatives / management have a ‘can do’ approach”

Savoy Hotel project information:

Main Contractor: Chorus Group Ltd
Project Value: £5.5m
Commencement Date: March 2009
Duration: 53 Weeks
Sector: Hotel / Leisure
Scope of Work: Partitioning , Dry lining & Suspended ceilings